Harbor Road, 829 Days Later: Nine Stages Between Stony Brook and Its Mill Pond

Broken end of a village road behind orange barriers beside a drained, overgrown pond basin and a historic mill in late autumn

On the night of August 18, 2024, the New York State Mesonet station at Stony Brook recorded 9.4 inches of rain in 24 hours, a total the state described as a 1-in-1,000-year event at that location. The dam holding back Stony Brook’s Mill Pond gave way in the storm, Harbor Road went with it, and more than 11,000 cubic yards of water poured into Stony Brook Creek. As of the last public updates, the road had not been rebuilt; by November 25, 2026, that makes 829 days. A year after the storm, News 12 reported that weeds and trees now grow where the pond had been.

Officials on restoring Stony Brook's Mill Pond after the August 2024 storm, from the YouTube channel CBS New York.

A Road That Belonged to Someone

The ownership question took more than a year to settle

For months after the collapse, it was unclear who was responsible for fixing it. Harbor Road crossed the dam on the route between Stony Brook and the Village of Head of the Harbor. By August 2025 the Town of Brookhaven was claiming the Ward Melville Heritage Organization owned it and said no FEMA application had gone in because the organization would not sign the forms. The organization disputed the claim, saying the town had maintained the road before it collapsed.

News 12 Long Island reported in October 2025 that the heritage organization had initially denied owning the property and had not sought federal disaster funds. In August 2025, the organization proposed splitting repair costs among the town, Suffolk County and the village, without FEMA. The Village of Head of the Harbor sued; News 12 did not report the filing date. By October 2025, under public pressure and with the lawsuit pending, the organization joined the town and the village in a joint statement that settled the point in one line: “WMHO is the owner of the property where Harbor Road and the dam are located.” The organization also sent documentation to FEMA.

Residents had made their own position clear well before that. In May 2025, News 12 counted close to 200 people at a rally demanding the road and pond be repaired. At that rally, Dr. Richard Rugen, chair of the heritage organization’s board, argued that it was a public road and questioned why a not-for-profit corporation would be expected to fix it.

The drained bed of a former mill pond overgrown with grasses and young trees, with a historic shingled grist mill in the background under a gray late-autumn sky

Where the $9 Million Comes From

State budget money, earlier state discretionary funds and a federal share

The money came in stages. Governor Kathy Hochul had first committed $2.75 million in discretionary funding after conversations with Brookhaven Town Supervisor Dan Panico. Assemblywoman Rebecca Kassay’s office later announced that the 2026-2027 state budget set aside a minimum of $6.5 million, which includes the governor’s earlier $2.75 million, for the Mill Pond dam and Harbor Road, drawn from a $20 million Suffolk County resiliency allocation. That sum, the release said, joins $2.5 million in federal funding already secured.

On June 18, 2026, the governor’s office folded the Harbor Road money into a $28.5 million package of Suffolk resiliency projects that also included $12 million for the Asharoken Avenue seawall and $8 million for the Blydenburgh dam and Stump Pond, where state dam safety staff had also been working after the August 2024 storm. In that announcement, Panico described the repair costs as beyond the means of the Ward Melville Heritage Organization, “which owns the dam and the roadway,” and said that with contributions from the governor and Congressman Nick LaLota, a total of $9 million had been brought forward.

None of the public statements reviewed for this article give a total cost for rebuilding the dam and road. Whether $9 million covers it, and what share the town or the heritage organization would carry beyond that, has not been published.

Nine Stages on One Web Page

The heritage organization publishes its own timeline

The clearest account of where the project stands comes from the owner. The Ward Melville Heritage Organization keeps a page titled Road to Recovery, which lays out nine stages:

  • Stage One, grist mill study: completed between February and March 2025
  • Stage Two, soil borings: completed between May and July 2025
  • Stage Three, hydraulics and design concepts: completed November 2025
  • Stage Four, downstream study: completed mid-February 2026
  • Stage Five, conceptual plans: completed March 2026
  • Stage Six, construction plans and permitting: in process, with construction plans described as on schedule as of July 7, 2026, and permit applications to follow immediately
  • Stage Seven, advertising for contractors: a municipal step, estimated at 30 days
  • Stage Eight, bids, contractor review and contract preparation: a municipal step, estimated at three to four months
  • Stage Nine, construction: estimated at one year, though the page notes some contractors believe the work could take four to five months, and that this depends on only the Town of Brookhaven section being rebuilt

The timing of permits is the open variable. The organization’s page says only that it depends on review by the regulatory agencies. The page marks Stages Seven and Eight as municipal steps. Supervisor Panico, quoted in Kassay’s release, said the plans will eventually be turned over to the Town of Brookhaven for build-out.

An engineer's rolled site plans and a hard hat on the hood of a truck parked beside a temporary road barrier and orange fencing at the edge of a washed-out road, overcast autumn light

The Most Recent Public Estimate

The town highway superintendent hopes to bid this winter

In August 2026, on the second anniversary of the storm, News 12 reported that applications to the state Department of Environmental Conservation were out for signatures and that construction plans were expected to be ready by the end of that month. Brookhaven Highway Superintendent Daniel Losquadro gave the station the most specific public target so far: “I’m hoping we can have an approved design and go out to bid this winter so we can start construction next year.”

Combining that target with the heritage organization’s own estimates gives a rough range, and it is only arithmetic: no party has published a construction start date. A winter bid, followed by three to four months of contractor selection, puts a construction start in the spring or summer of 2027 at the earliest. A one-year build would carry the work into 2028, and a four-to-five-month build, which the page ties to rebuilding only the town’s section, would finish in late 2027. Every one of those dates depends on permits that, as of the last public update, had not been reported as approved.

What the Gap Has Meant for the Neighborhood

A missing link between two villages

The washout cut off what News 12 called a key route between Head of the Harbor and Stony Brook. One Head of the Harbor resident, Beth Zweig, called it “a literal hole in the heart of Stony Brook” and said much time had been wasted “pointing fingers.” Another, Dori Scofield of Stony Brook, told the station her grandchildren do not know what the duck pond looked like.

For buyers looking near the village, the closed road and drained pond are a current condition with a public paper trail. The heritage organization’s page, the town highway department and the offices of local officials are the places that track it. The earlier Maison Pawli guide to an afternoon in Stony Brook Village covers the rest of the village, which remained open throughout.

A historic white clapboard grist mill beside an empty, grassy pond basin at golden hour, with bare trees and a stone retaining wall in the foreground

The Pond Itself

Restoring the road and restoring the water are tied together

The pond drained when the dam failed, so its return depends on the dam. The heritage organization’s stages cover hydraulics, downstream effects and design for that structure, and Kassay’s office has framed the project as restoring the Mill Pond dam and reopening Harbor Road in a single effort. The published plans do not say how long a rebuilt dam would take to refill the pond, or whether the pond would return at the same size and depth it had before August 2024. Neither the heritage organization nor the town has published those details.

The last public status, the heritage organization’s July 7 update and News 12’s August report, had construction plans nearly done and DEC applications awaiting signatures. No approved permit had been reported.